This article details how to edit the resource allocation percentage on a project plan task with Web Plan Manager or Windows Plan Manager.
How-To
Task: To manually edit the resource allocation percentage on a project plan task using Web Plan Manager
Instructions
Step 1 - Do not "Check Out" the plan.
Step 2 - Select the entire task row.
Step 3 - Right-click and select Task Details.
Step 4 - Select Resources tab.
Step 5 - In the "Action" column select Edit.
Step 6 - Enter new "PCT".
Step 7 - Select Save in the "Action" column.
Step 8 - Close window and select Refresh in upper left-hand corner.
Outcome
Resource allocation on a project plan task will be updated.
Back to top
Task: To manually edit the resource allocation percentage on a project plan task using Windows Plan Manager
Instructions
Step 1 - Check Out the plan.
Step 2 - Double-click in the task row.
Step 3 - Select the Resources tab.
Step 4 - Drag the slider in the "% Assigned" column.
Step 5 - Close window.
Step 6 - Save and Check-In.
Outcome
Resource allocation on a project plan task will be updated.