TeamDynamix: Project Status and Project Health Choices and Definitions

Summary

This article details the project status and project health choices and definitions.

Body

Summary

This article details the project status and project health choices and definitions.

Purpose: Project Status and Project Health choices and definitions
Intended Audience:  TeamDynamix Project Managers
Environment:  TeamDynamix Projects
 

Project Health

Green: Project is on track (project is meeting defined objectives in scope, on schedule, and on budget).
Yellow: Project is at risk, but corrective actions have been identified.
Red: Project is at risk, no corrective actions yet identified.
No Status: This may only be used when the project is not yet in process (see below).

 

Project Status

New (Not Started): for any approved project in the pipeline, but not yet started. 

  • At this stage you may be gathering high-level requirements but there is no planning of any significance underway.
  • The project has been approved through the normal request process (if applicable) and is simply being added to the queue.

In Process: A project belongs in this status once work begins.

  • Project work includes scheduling, identifying the project team and/or resources, developing KPIs, and naturally any implementation and execution.
  • A project will remain in this status until Completed, Cancelled, or put On Hold.
  • When a project is in process, Project Health should be Red, Yellow, or Green.

On Hold: Use for a project that you want/expect to complete, on which work has paused.

  • There aren't any backend features triggered when a project is placed "On-Hold". It is simply a status and visual indicator that the project is "paused".
  • The project is still active and any resources on the project are still scheduled, meaning the project still impacts resource availability.
  • Resources can still log time/expenses against an on-hold project and still work tasks, issues, etc.

Completed or Cancelled: These project status indicators are only available when Closing a project.

 

Need additional help?

Visit the TeamDynamix area in the Knowledge Base

To request service, report an issue, ask questions, or request training, submit a TeamDynamix Application Administration Support Request

Details

Details

Article ID: 807
Created
Fri 7/19/19 5:37 PM
Modified
Fri 5/30/25 11:40 AM
Applicable Institution(s):
Keene State College (KSC)
Plymouth State University (PSU)
University of New Hampshire (UNH)
USNH System Office