Summary
This article details how to close or cancel a project once completed in TeamDynamix.
How-To
Task: To close out a completed project.
Instructions
Step 1 - Go to Applications menu and click on Projects application.
Step 2 - Click on the name of the relevant project in the left-hand navigation.
Step 3 - Before closing the project, review it to ensure that all Tasks and Issues are marked as completed:
- Select Issues and ensure any open issues have been closed.
- Select Plans. Review the tasks to make sure all are completed.
- When finished, Check-In and close the plan window.
Step 4 - Return to the Projects main screen. Under the name of the related project select Manage to display the details of the project.
Step 5 - Select the green Actions button, and then Close. This will launch a "Close Project" wizard.
Step 6 - Follow the steps in the wizard to close out your project:
-
"Copy files to File Cabinet" (if applicable).
-
"Close unfinished items".
Note: It is not recommended for Project Managers to close out unfinished items from the wizard, unless you are closing an Operational Project, or Cancelling a project. For all other projects with items remaining to be closed, it is recommended that you exit the wizard and return to Step 1, above
-
"Request Feedback" (Skip this section).
-
"Choose the closed project status and health":
-
Select Inactive.
Note: An inactive project will no longer allow time to be recorded to that project effort. Project Managers are encouraged to allow a grace period of about a week for time recording prior to closing the project out in order to facilitate time entry.
-
Select a status of Completed or Cancelled, as applicable.
-
Set Percent complete (If Completed, this should be 100%. If Cancelled this may reflect the progress before termination.)
-
Add Comments.
-
Click Save.
Note: If your project has been cancelled, follow the steps above for closing a completed project in TeamDynamix, however you can optionally eliminate Step 3. Instead, you can simply close all Tasks and Issues through the "Close Project" wizard in Step 6.
Outcome:
Completed project will be closed.